Clean Water Institute
Table 2.Summary of Bank Erosion Potential based on Particle Size along Lycoming Creek*
Summer 2002**

Total Banks
Erosion Potential Number Percent
Low 7 6.48%
Moderate 72 66.67%
High 29 26.85%
Total 108  

Right Banks
Erosion Potential Number Percent
Low 3 5.17%
Moderate 35 60.34%
High 20 34.48%
Total 58  

Left Banks
Erosion Potential Number Percent
Low 4 8.00%
Moderate 37 74.00%
High 9 18.00%
Total 50  

* Study area between Roaring Branch and Lower Heshbon Road
**Completed by Lycoming College Clean Water Institute Interns

 